Bayfancy Residence Moves Forward with Key Construction Milestones Set for Year-End

As the final months of 2026 unfold, Bayfancy Residence continues to take shape in Hulhumalé, with a series of carefully coordinated construction activities bringing the development closer to its envisioned form. From the gradual refinement of residential interiors to the evolving architectural exterior, the project is progressing through an important stage of its construction journey.

image.png 1.69 MB
The development has now reached 76% overall completion as of 31 October 2026, reflecting continued progress across multiple areas of construction. With a structured programme guiding the remaining activities, the engineering and construction teams are working towards a series of defined milestones scheduled for November and December.

Recent progress has been particularly evident across the residential floors, where interior finishing works are advancing in stages. Ceiling installation has been completed from the 10th to the 15th floors, while wall and ceiling surface preparation and tiling have progressed across the upper levels. Floor levelling, bathroom waterproofing, and essential electrical and plumbing installations have also reached significant stages of completion throughout the building.

image.png 1006.53 KB
Alongside these interior developments, work on the building's exterior continues to advance. The installation of aluminum doors and windows, completion of external drainage systems, and progressive removal of scaffolding are contributing to the gradual emergence of the residence's architectural identity.
image.png 1.39 MB
Looking ahead, the construction programme places particular emphasis on completing key interior and exterior works before the end of the year. Electrical and plumbing pipework across the 2nd to the 17th floors is scheduled for completion by the end of November, followed by further progress in floor levelling, bathroom waterproofing, ceiling installation, surface preparation, and tiling throughout December.
image.png 1.19 MB
One of the most notable milestones planned for December is the completion of aluminum door and window installation and exterior façade finishing, alongside the removal of external scaffolding across the building by the end of the year. These developments are expected to mark a significant visual transformation, allowing the building's architectural design to become more fully apparent.

The sequence of these activities reflects the importance of planning and coordination in a development of this scale. Each stage of construction is connected to the next, requiring the alignment of structural finishing, building services, interior installations, and exterior works. By progressing through clearly established milestones, the project team continues to maintain an organized approach to construction while keeping attention on the quality and details of the finished residence.

image.png 1.32 MB
As Bayfancy Residence moves into the next phase of its development, the focus remains on steady execution, technical coordination, and the careful completion of each remaining stage. The progress achieved so far, together with the programme established for the months ahead, reflects the continued commitment to bringing the vision of Bayfancy Residence to life.