Bayfancy Residence Construction Update - 8th January 2026
📌 Current Construction Progress
• 🧱 Masonry works of the 15th Floor completed
• 🧱 Masonry works of the 16th Floor 80% completed
• 🧱 Masonry works of the 17th Floor 50% completed
• 🧱 Masonry works of the 18th Floor 50% completed
• ⚡ Initial MEP works on the 3rd Floor completed
• 🪨 Plastering works of the 8th Floor completed
🚧 Ongoing Operations
• 🧱 Masonry works on the 16th, 17th, and 18th Floors are actively progressing
This update reflects the steady, methodical progress of Bayfancy Residence as we move through key structural and service milestones. Each stage is planned and executed in sequence to maintain quality, coordination, and construction discipline.
Through our Journey to Handover series, we share these updates as a commitment to transparency and accountability. Every completed floor and ongoing operation brings us closer to timely delivery, reinforcing our promise to hand over homes that meet both schedule and standards.