Bayfancy Residence – 18F Slab Completed
Update
23rd-September-2025
🏗️ Bayfancy Residence – 18F Slab Completed
📅 23rd September 2025
📌 Current Construction Progress:
• ✅ Completion of 18F slab concrete casting
• ✅ Completion of the Masonry works of 7F
🚧 Ongoing Operations:
• 🔧 Construction efforts are presently focused on the formwork of the Terrance slab.
• 🧱Masonry works on the 8F is 75% completed
📐 from concept to reality, every floor represents a commitment to architectural precision and aesthetic excellence, ensuring Bayfancy Residence stands as a landmark of luxury living in Hulhumalé.
🏡 Bayfancy Residence continues its mission to “Create Personalized Smart Luxury Living”, setting benchmarks in modern urban lifestyle.
👷♂️ Our team remains dedicated to refining living spaces and creating superior lifestyles for our residents.