Bayfancy Residence – 11F Slab completed
Update
12th-July-2025
🎯 Bayfancy Residence – 11F Slab completed
🗓️ 12th July 2025
🏆 Current Construction Progress:
✅ 🏢 Completion of 11F slab concrete pouring
✅ 🧹 The construction of internal partition walls on the 2nd floor has been completed
🚀 Ongoing Operations:
⏳ 📶 Reinforcement and formwork installation for the 12th floor slab in progress
📊 🧱 The construction of interior partition walls on the 3rd floor has been 50% completed
💎 Bayfancy Residence remains steadfast in its mission to "create personalized smart luxury living" meticulously crafting benchmark-quality residences.
👨🔧 Bayfancy team consistently dedicated to refining residential environments and crafting superior lifestyles for our residents.